Formal Inquiries
Huddlesford report and recommendations
Rail Safety and Standards Board has issued its formal inquiry report
into the derailment of a freight train at Huddlesford on the 15 July 2003.
The formal inquiry was convened under independent chairmanship and included
representatives on the panel from the involved parties. As with all such
inquiries the panel's task was to establish the immediate and underlying
causes of the accident and make recommendations to prevent or reduce the
risk of recurrence.
Sequence of events
Train 4L92, a Freightliner service from Ditton to Felixstowe, was derailed
at approximately 115 miles 280 yards on the West Coast Main Line between
Lichfield and Tamworth.
The train was hauled by a Class 90 locomotive and was conveying 22 vehicles,
15 of which were empty and the remainder laden to differing extents. Derailment
took place immediately south of underbridge number 95 at Huddlesford.
The eighth and ninth vehicles derailed rear bogie only and the following
vehicles derailed all wheels. The train divided between the eleventh and
twelfth vehicle and the locomotive came to a stand some 740 metres after
the point of derailment with the eighth vehicle having travelled some
566 metres in the derailed condition.
Conclusions
The panel found a number of underlying and immediate causes surrounding
the derailment, these were:
- Train 4L92 derailed immediately south of underbridge number 95 at
Huddlesford in response to a significant lateral misalignment of the
track.
- The lateral misalignment was a heat induced buckle and resulted from
a probable low stress free temperature and a combination of individual
track features. Each of the track features in isolation was unlikely
to be sufficient to trigger a buckle.
- Derailment occurred at 1638hrs approximately on a very hot and sunny
day with rail temperatures in the region of 40°C.
- There were indications that the stress free temperature at the point
of derailment was below the specified design values.
- The shoulder ballast profile over underbridge number 95 and immediately
to the south was deficient.
- There were voids of the order of 4 to 6mm below the sleepers immediately
south of underbridge number 95.
- There was poor vertical track geometry and cross level variation
over underbridge number 95 and immediately to the south.
- The track over underbridge number 95 comprised hardwood timber sleepers
that has reduced lateral stability by comparison with concrete.
Recommendations
The report makes recommendations for improvements in a number of key
areas and these are summarised as follows:
- The Project Maintenance Strategy defining the responsibilities of
the maintenance contractor, renewal contractor and Network Rail should
be reviewed for adequacy. In particular it should encourage timely maintenance
of newly installed track so that defects are not allowed to develop
closer to safety limits than is desirable.
- The revised Project Maintenance Strategy defining the responsibilities
of the maintenance contractor, renewal contractor and Network Rail be
fully briefed and implemented for track renewal sites on the West Coast
Main Line (South).
- Individual relatively minor defects can often have much greater significance
if they occur in combination. The recording of all minor track defects
should be encouraged so that they can be viewed as a complete picture.
- Timber sleepers are common in both new and existing CWR. Some installations
are very short, that is a few sleepers. There should be clarity and
consistency with regard to the assumed stability of such CWR.
- The effect on rail stress in CWR as a result of major disturbance
such as occasioned by ballast cleaning should be assessed.
- RT/CE/S/011 should be reviewed to clarify the position with regard
to locations where a full ballast shoulder cannot be installed.
- A review of the robustness of the Fastclip fastening system to damage
from derailed vehicles and the potential safety consequences should
be undertaken.
Rail Safety and Standards Board has issued a full copy of the report
to each member of the Railway Group and the other organisations involved
in the accident. All recipients of the report need to review the findings
and recommendations and take actions where appropriate to address identified
deficiencies within their own systems. Rail Safety and Standards Board
will track the industry's response to this report.
|