Formal Inquiries
Kings Cross report and recommendations
Rail Safety and Standards Board has issued its formal inquiry report
into the derailment of a passenger train at Kings Cross on 16 September
2003. The formal inquiry was convened under independent chairmanship and
included representatives on the panel from the involved parties. As with
all such inquiries the panel's task was to establish the immediate and
underlying causes of the accident and make recommendations to prevent
or reduce the risk of recurrence.
Sequence of events
Work to overcome a defective cast crossing, (a track component associated
with a set of points), was carried out under a possession at Kings Cross
Station. The planned possession was due to end at 0545hrs but overran
until 0657hrs.
At this stage, the defective crossing had been removed and replaced
with plain rail, making several of the normally available routes from
platform 4 unavailable. Correct procedures were not followed that should
have ensured that the unavailable route could not be set by the signaller.
At the departure time for the 0700hrs Kings Cross to Glasgow Central
train, the signaller was able to set a route and clear the signal for
a route where a section of rail was missing. The driver approached 15mph
(24km/h) when he noticed the new rail in place of the crossing and the
gap in the left hand rail, and he applied the emergency brake. The locomotive
derailed, there were no injuries to passengers or crew.
Conclusions
The panel found a number of underlying and immediate causes surrounding
the derailment, these were:
- The absence of clips, scotches and padlocks on the switch ends of
appropriate points.
- The status of the signalling system that allowed the signaller to
set and signal a train over a route with incomplete track.
- The decision taken to carry out the permanent way work near one set
of points and on another set points without preparation and use of a
method statement.
- Insufficient time allowance before the possession to plan the work.
- Failure to order and have available a suitable crossing as a replacement
for a track component known to have a long standing and worsening unrepairable
defect.
- Communication failures between person in charge of possession, signaller
and signal engineering staff.
Recommendations
The report makes recommendations for improvements in a number of key areas
and these are summarised as follows:
- Order request tracking procedures should be reviewed.
- When a short notice possession has been planned, requests to undertake
additional work within the same possession should only be accepted after
the full implications have been discussed.
- When any part of a switch or crossing is replaced, resulting in a
single route over the switch and crossing, the switch blades must be
clipped, scotched and padlocked.
- Method statements are prepared for all tasks and used to brief the
staff involved.
- Proposals to restrict routes by removing signal links must be documented
and checked by an independent competent person.
- In all situations when the signalling is to be handed back after
completion of work with restrictions, the appropriate form (RT3187)
must be used.
- Shift handover practices and documentation should be reviewed in
Kings Cross signal box.
- Targeted audits and surveillance assessments of new safety critical
procedures should be introduced.
- The testing and inspection frequency established to monitor track
component defects should be related to the severity of the defect and
its rate of propagation.
- Track Engineering standards should be revised to make clear under
what circumstances allowances and dispensations are open to engineers.
- The Rule Book should have clear unambiguous instructions on the situations
in which points must be clipped.
- Possession requirements shown in Weekly Operating Notices and Late
Notices should always give an indication of work to be carried out when
this will result in restrictions to signalling equipment on hand back.
- Discussions should be held with the HSE to agree the processes to
be used to obtain information from vehicle based data recorders.
Rail Safety and Standards Board has issued a full copy of the report
to each member of the Railway Group and the other organisations involved
in the accident. All recipients of the report need to review the findings
and recommendations and take actions where appropriate to address identified
deficiencies within their own systems. Rail Safety and Standards Board
will track the industry's response to this report.
|