Trials with the 3 piece mould SkV-F (SC) thermit welding process using a modified bottom mould section (TM-MET-057)

Last updated on 21 June 2013 2:49
The SkV-F-(SC) process, which utilises a three piece mould,was developed for situations where welds may require periodic replacement (such as at S & C layouts when replacing individual units), and a requirement of the process was that it should be capable of welding rail of differing profiles due to wear...
Author(s): Johnson R.S.
Organisation(s): British Rail Research ;
1980
United Kingdom
Log in or register to continue
Register for free individual access
  • Unlock research, articles and more
  • Get updates on RSSB’s activities