Improving power change over systems to deliver cost and operational benefits
The growing number of multi-mode trains and discontinuous electrification schemes means there is a variety of power change over (PCO) setups.
PCO is the process by which rolling stock switches its source of power. This can be from an overhead line to third rail electrification, from diesel to electric, or from battery to diesel.
PCO systems have been used since the 1970s. But they are now more common and more complex due to the increased use of multi-mode trains.
Many passenger and freight journeys use these systems. But because they are not consistent, drivers might notice a ‘patchwork’ of varying PCO systems.
There was a limited understanding of how appropriate different solutions are for new change over sites and multi-mode trains and how to manage and reduce variability.
We assessed the safety, performance, and operational impacts of PCO setups. We looked at incidents and failure modes, and we found ways to mitigate PCO complexity.
We found that current PCO systems are complex and limited in their interoperability. Our research suggests ways to simplify these systems. For example, industry could move away from proprietary on-train databases. It could also avoid signalling-level complexity.
We also gave recommendations on how new PCO setups should be deployed. This includes strategies to standardise PCO locations and driver training for passenger and freight journeys.
We also suggested some ways to provide assurance with PCO design. For instance, industry could embed human factors in the concept stage. It could also improve the collection of PCO incident data.
Our research can benefit industry in a few ways. One is by helping prevent design-stage issues for PCO systems. In practice, this will be achieved by integrating human factors, operability, and maintainability.
The findings can also help industry reduce the cost and complexity of PCO setups. This is because they support project teams in finding ways to standardise how they are designed and operated.
The research also helps manufacturers develop safer and more reliable PCO systems. It does this by recommending how human factors can be integrated during the concept stage. Better collection of PCO incident data could also improve risk management.
Using the findings of this research could lead to better use of existing electrification. For instance, it could lead to improving pantograph timing and making changes to overhead line geometry.