Welcome to the standards catalogue. Search by entering a title, keyword(s) or document number below (e.g. "platform" or 7016 or GERT8000-TW1) or use the filters to narrow down all options. Boolean search operators such as AND, OR, (-) minus sign and ("") quotes for exact match may also be used.
Lead/Supporting Committee(s)
Issue Date
From: To:Lead/Supporting Committee(s)
Document Type
Issue Date
From: To:Engineering Design of On-Track Machines in Travelling and Working Modes
This document sets out requirements and guidance for the application of the BS EN 14033:2017 series for on-track Machines (OTMs) in their travelling…
RIS-1702-PLT Iss 2
March 2025
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
- Technical Notes 2
Medical Fitness Assessment
This document sets out requirements and guidance for the management of medical fitness assessment for safety critical workers on the GB mainline…
GOGN3655 Iss 2
March 2025
Withdrawn
- Briefing Notes: 1
RIS-3451-TOM Iss 1
March 2025
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
RIS-3452-TOM Iss 1
March 2025
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
Reference Limits for Freight Wagon Defects
This document sets out the criteria for addressing defects in freight wagons arising during operation, and the restrictions on their use that apply.
RIS-2702-RST Iss 2
March 2025
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
Lineside Operational Signs
This document sets out requirements, rationale and guidance for the application of lineside operational signs published in the RSSB catalogue. It also…
RIS-0733-CCS Iss 1.2
March 2025
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
Provision of Signage at Power Changeover Locations
This document sets out requirements and guidance for provision of signage at power changeover locations for multi-mode rolling stock.
RIS-3784-TOM Iss 1
March 2025
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
Requirements for the operation of freight trains and the conveyance of dangerous goods by any train
This document sets out requirements and guidance relating to the safe operation of freight trains and the safe movement of dangerous goods.
RIS-3781-TOM Iss 1
March 2025
Withdrawn
- Briefing Notes: 1
- Impact Assessments 2
Maintaining the Visibility of Signals and Operational Signs
This document sets out requirements and guidance to ensure that the visibility of signals and operational signs are not adversely affected during the…
RIS-8034-CCS Iss 1
March 2025
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
Junction signal sighting
This technical note has been issued to help the industry manage the sighting of colour light junction signals. This document is responding to the RAIB…
TPWS receiver aerial location
This technical note will help industry identify the risks associated with mounting the Train Protection and Warning System (TPWS) receiver aerial…
Psychometric Assessment in Train Driver Selection
This document sets out requirements and guidance on the psychometric assessment used during the selection process for train driver candidates who will…
RIS-3751-TOM Iss 3
December 2024
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
General duties of an individual working alone (IWA)
This handbook is for those personnel with general duties of an individual working alone (IWA).
GERT8000-HB6 Iss 7
December 2024
Withdrawn
- Impact Assessments 1
- Deviations 1
General duties of a controller of site safety (COSS)
This handbook is for those personnel who have the general duties of a controller of site safety (COSS).
GERT8000-HB7 Iss 8
December 2024
Withdrawn
- Impact Assessments 1
- Deviations 11
Duties of the machine controller (MC) and on-track plant operator
You will need this handbook if you carry out the duties of the machine controller (MC) and on-track plant operator.
GERT8000-HB15 Iss 6
December 2024
Withdrawn
- Impact Assessments 1
Defective or isolated vehicles and on-train equipment
You will need this module if you carry out the duties of a driver, guard, signaller or train preparer. It sets out the operational instructions to be…
GERT8000-TW5 Iss 12
December 2024
Withdrawn
- Impact Assessments 1
- Technical Notes 2
Personnel asking for trains to be stopped form
This form is used by signallers to record the details when personnel ask for a line to be blocked for their own protection when going on or near the…
Level crossings - signallers' regulations
You will need this module if you carry out the duties of a signaller in an area where there is a level crossing.
GERT8000-TS9 Iss 4.1
December 2024
Withdrawn
- Impact Assessments 1
Preparation and movement of trains
You will need this module if you carry out the duties of a driver, guard, shunter, signaller, train preparer or competent person.
GERT8000-TW1 Iss 19
December 2024
Withdrawn
- Impact Assessments 2
- Technical Notes 1
- Deviations 2
General duties and track safety for track workers
This handbook is for those personnel who need to go on the operational railway to carry out their duties, with the exception of a train driver, guard,…
GERT8000-HB1 Iss 7
December 2024
Withdrawn
- Impact Assessments 1
Level crossings - drivers' instructions
You will need this module if you carry out the duties of a driver.
GERT8000-TW8 Iss 9.1
December 2024
Withdrawn
- Impact Assessments 1
IWA, COSS or PC blocking a line
You will need this handbook if you carry out the duties of a IWA, COSS or PC blocking a line.
GERT8000-HB8 Iss 9
December 2024
Withdrawn
- Impact Assessments 1
- Deviations 1
Directional arrows
This document provides design details for sign AJ10 - Directional arrows.
Advance lower pantograph (temporary power changeover)
This document provides design details for sign AJ12 - Advance lower pantograph (temporary power changeover).
Warning of Traction System Changeover
This document provides design details for sign AJ04 - Warning of traction system changeover.
Indication of route
This document provides design details for sign AJ11 - Indication of route.
Lower pantograph (temporary power changeover)
This document provides design details for sign AJ13 - Lower pantograph (temporary power changeover).
Changeover to or from self-powered
This document provides design details for sign AJ08 - Changeover to or from self-powered.
Changeover to Overhead Electric Traction
This document provides design details for sign AJ07 - Changeover to Overhead Electric Traction.
Do not raise pantograph
This document provides design details for sign AJ09 - Do not raise pantograph.
Do not raise pantograph (temporary power changeover)
This document provides design details for sign AJ15 – Do not raise pantograph (temporary power changeover).
Document Type
Issue Date
From: To:Misuse of MEWPs
This poster is provided by the M&EE Networking Group to remind industry not to misuse MEWPs during work activities.
Plant Exclusion Zones
This poster is provided by the M&EE Networking Group to remind industry about the necessity to keep personnel clear from areas around working…
Emergency Haulage by OTMs
This Code of Practice details the haulage capabilities of on-track machines (OTM). It should be followed by any route or operator control when…
Use and Maintenance of Full Electric/Hybrid Powered OTP
This Code of Practice details best practice for use and maintenance of battery or hybrid powered OTP. It defines best practice and industry guidance…
Injection Injury
This poster details the actions to be taken following a hydraulic injection injury.
Cross Tracking of On Track Plant
OTP must only be on/off tracked within a Possession. OTP is not permitted to cross track under Line Blocks.
AFFF Fire Extinguishers
This poster is provided by the M&EE Networking Group to remind industry about the potential for AFFF fire extinguishers to freeze in cold weather.…
RRV Braking
This poster is provided by the M&EE Networking Group to remind industry is a reminder that road-rail vehicles when in rail mode take a lot longer to…
Piling using OTP
This Code of Practice details guidance on the arrangements for controlling the risks when planning and undertaking piling operations on the railway…
Plant Activities with Any Line Open