Standards Catalogue
Welcome to the standards catalogue. Search by entering a title, keyword(s) or document number below (e.g. "platform" or 7016 or GERT8000-TW1) or use the filters to narrow down all options. Boolean search operators such as AND, OR, (-) minus sign and ("") quotes for exact match may also be used.
Lead/Supporting Committee(s)
Issue Date
From: To:Maintaining the Visibility of Signals and Operational Signs
This document sets out requirements and guidance to ensure that the visibility of signals and operational signs are not adversely affected during the…
RIS-8034-CCS Iss 1
March 2025
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
Train Driver Manual
The Rule Book manuals have been produced to provide end-users with access to the content of the Rule Book that is relevant to their roles, e.g.…
Raise pantograph (temporary power changeover)
This document provides design details for sign AJ14 - Raise pantograph (temporary power changeover).
Signaller and Signalling Technician Manual
The Rule Book manuals have been produced to provide end-users with access to the content of the Rule Book that is relevant to their roles, e.g.…
GERM8000-signallersignallingtechnician Iss 14.1
June 2025
Withdrawn
Junction signal sighting
This technical note has been issued to help the industry manage the sighting of colour light junction signals. This document is responding to the RAIB…
TPWS receiver aerial location
This technical note will help industry identify the risks associated with mounting the Train Protection and Warning System (TPWS) receiver aerial…
Psychometric Assessment in Train Driver Selection
This document sets out requirements and guidance on the psychometric assessment used during the selection process for train driver candidates who will…
RIS-3751-TOM Iss 3
December 2024
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
Guidance on the Common Safety Method for Risk Evaluation and Assessment
This document gives guidance on application of the principles in the Common Safety Method for Risk Assessment and Evaluation.
GEGN8646 Iss 1
December 2024
Withdrawn
- Briefing Notes: 1
Identification of roller bearing defects
This document sets out requirements and guidance for the identification and recording of roller bearing defects at overhaul, for taper, cylindrical…
RIS-2709-RST Iss 1
December 2024
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
- Technical Notes 1
Lead/Supporting Committee(s)
Document Type
Issue Date
From: To:Reporting of adverse events
This technical note will help industry to understand the reporting systems for safety related issues provided by the Rail Safety and Standards Board…
Lineside Operational Signs - Product Requirements
This document sets of the requirements of lineside operational signs that support technical compatibility with rail vehicle exterior lighting and…
GIRT7033 Iss 4
June 2023
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
- Deviations 1
Rail Vehicle Structures and Passive Safety
This document sets out requirements for the design and integrity of primary and secondary rail vehicle structures, including interior crashworthiness.
GMRT2100 Iss 6.1
June 2023
Withdrawn
- Briefing Notes: 2
- Impact Assessments 1
Management of Safety-Related Rail Vehicle Defects
This document defines requirements for recording, analysing and reporting safety-related defects, faults and failures on rail vehicles, plant and…
RIS-8250-RST Iss 1
June 2023
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
- Amendments: 2
Urgent High-Risk Defect Report Form
In the event that the NIR-Online system is unavailable, details of urgent high-risk defects, faults and failures shall be shared by completing and…
Communication of urgent operating advice
This standard sets out requirements, rationale and guidance for reporting and communicating urgent operating safety information.
RIS-3350-TOM Iss 1
June 2023
Withdrawn
- Briefing Notes: 1
- Impact Assessments 1
Engineering change (software and firmware)
This technical note provides signposts to existing standards and good practice in engineering change management relating to software and…
Freight coupler loads
This technical note will help industry assess the ability of a locomotive to haul loads over a route. It focuses on coupler load capacity and…
Fire-related properties of batteries
This technical note sets out options for improving fire performance of batteries in use on GB mainline rolling stock, and the factors which may need…
Directional arrows
This document provides design details for sign AJ10 - Directional arrows.
Advance lower pantograph (temporary power changeover)
This document provides design details for sign AJ12 - Advance lower pantograph (temporary power changeover).
Warning of Traction System Changeover
This document provides design details for sign AJ04 - Warning of traction system changeover.
Indication of route
This document provides design details for sign AJ11 - Indication of route.
Lower pantograph (temporary power changeover)
This document provides design details for sign AJ13 - Lower pantograph (temporary power changeover).
Changeover to or from self-powered
This document provides design details for sign AJ08 - Changeover to or from self-powered.
Changeover to Overhead Electric Traction
This document provides design details for sign AJ07 - Changeover to Overhead Electric Traction.
Do not raise pantograph
This document provides design details for sign AJ09 - Do not raise pantograph.
Do not raise pantograph (temporary power changeover)
This document provides design details for sign AJ15 – Do not raise pantograph (temporary power changeover).
Document Type
Issue Date
From: To:Misuse of MEWPs
This poster is provided by the M&EE Networking Group to remind industry not to misuse MEWPs during work activities.
Plant Exclusion Zones
This poster is provided by the M&EE Networking Group to remind industry about the necessity to keep personnel clear from areas around working…
Emergency Haulage by OTMs
This Code of Practice details the haulage capabilities of on-track machines (OTM). It should be followed by any route or operator control when…
Use and Maintenance of Full Electric/Hybrid Powered OTP
This Code of Practice details best practice for use and maintenance of battery or hybrid powered OTP. It defines best practice and industry guidance…
Injection Injury
This poster details the actions to be taken following a hydraulic injection injury.
Cross Tracking of On Track Plant
OTP must only be on/off tracked within a Possession. OTP is not permitted to cross track under Line Blocks.
AFFF Fire Extinguishers
This poster is provided by the M&EE Networking Group to remind industry about the potential for AFFF fire extinguishers to freeze in cold weather.…
RRV Braking
This poster is provided by the M&EE Networking Group to remind industry is a reminder that road-rail vehicles when in rail mode take a lot longer to…
Piling using OTP
This Code of Practice details guidance on the arrangements for controlling the risks when planning and undertaking piling operations on the railway…
Plant Activities with Any Line Open
All plant activities that could foreseeably foul an open line require a documented ALO Plan, which must be approved by a Responsible ALO Manager.