COP0008 Iss 7

Code of Practice for Tandem Lifting with Two Excavator Cranes

Synopsis

This Code of Practice details the control measures to be applied when using two excavator cranes to lift a load simultaneously.

This Code of Practice applies to the use of two excavator cranes which normally lift loads independently, but which are required to occasionally lift a load in conjunction with another similar excavator crane using a process known as tandem lifting. This Code of Practice applies to both construction based and rail converted excavator cranes tandem lifting operations.

 

Summary Of Changes

New template and minor changes to clause numbering following review
Live
M and EE Networking Group: Code of Practice
Issued:
20/11/2024
Published:
01/03/2025

Details

Vehicle Assessment No
Supersedes COP0008 Iss 6