Menu

GERT8000-HB15 ERTMS Iss 3

Duties of the machine controller (MC) and on-track plant operator on ERTMS lines where lineside signals are not provided

Synopsis

You will need this handbook if you carry out the duties of the machine controller (MC) and on-track plant operator on ERTMS lines.

Summary Of Changes

RIS-1710-PLT Iss 1 - 'Rail Industry Standard for Engineering Certification of Railborne Plant' was published in December 2015 and this included the creation and accreditation of Plant Assessment Bodies (PABs). PABs now issue an Engineering Conformance Certificate (ECC). Amendments 8000-HB15 Iss 4 AM001 and 8000-HB15 ERTMS Iss 2 AM001 have now been incorporated into HB15 and HB15 ERTMS, to include reference to the ECC issued by PABs.

12 mnth review - No further action required.

Read full standard
register-icon
Registered
Live
Rule Book Handbook
Issued:
02/09/2017
Published:
02/09/2017
In Force:
02/12/2017
Last Review:
04/12/2018
Next Review:
12/02/2023

Details

Consultation Status Closed
Vehicle Assessment No
Supersedes GERT8000-HB15 ERTMS Iss 2
Lead Committee Traffic Operation and Management - TOM
Supporting Committee Control Command and Signalling - CCS
Supporting Documents GERT8000-RBBL Iss 30