GERT8000-OTP Iss 3
On-track plant (OTP)
Synopsis
Rule Book module GERT8000-OTP sets out the requirements for the placing and removing OTP from the line and its operation when travelling and working in a possession.
Read full standard

Registered
Withdrawn
Rule Book Modules:
On-track plant (OTP)
- Issued:
- 01/01/2007
- Published:
- 06/01/2007
- In Force:
- 02/06/2007
- Withdrawn:
- 04/06/2011
Details
Consultation Status | Closed |
Vehicle Assessment | No |
Supersedes | GERT8000-OTP Iss 2 |
Superseded By | GERT8000-HB15 Iss 1 |
Lead Committee | Traffic Operation and Management - TOM |
Supporting Committee | Plant - PLT |
Impact Assessments
![]() Registered |
11 EOC01 |
Deviations
![]() Registered |
05-118-DGN
Module OTP
06-109-DGN
On-track Plant
09-182-TNC
Authority for the OTP to move outside a work site. |